The following rates were approved by the Iowa Utilities Board and became effective on February 8, 2002.
Please note that these rate forms are saved as Adobe PDF files. If you do not have a PDF viewer, use this Adobe link to download one for free.
Rate 1 | Rate 2 | Rate 3 | Rate 4 | Rate 5 | Rate 8 | Rate 11 | Rate 12 | Rate 13 | Rate 14 | Rate 16
Riders for Rate codes and Tariffs : Rider 1 | Rider 4 | Rider 5 | Rider 6
Rate Code 1 :: Complete Tariff for Rate Code 1
Residential Service
Facility Charge: $13.50/month
Energy Charge:
First 400 kWh @ 12.90¢/kWh
Over 400 kWh @ 10.74¢/kWh
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 2 :: Complete Tariff for Rate Code 2
Residential All Electric Service
Facility Charge: $13.50/month
Energy Charge:
First 400 kWh @ 12.90¢/kWh
Next 800 kWh @ 10.74¢/kWh
Over 1200 kWh @ 8.97¢/kWh
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 3 :: Complete Tariff for Rate Code 3
Commercial, Industrial & Three Phase Farm Service
<75kW demand Jun, Jul, Aug, Dec, Jan, Feb
Facility Charge: $13.50 Single Phase/$30.00 Multi Phase
Energy Charge:
First 400 kWh @ 14.09¢/kWh
Over 400 kWh @ 10.55¢/kWh
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 4 :: Complete Tariff for Rate Code 4
Large Power Service
<75kW demand Jun, Jul, Aug, Dec, Jan, Feb
Optional for >25kW
Facility Charge: $40.00
Energy Charge:
First 100 kWh @ 8.13¢/kWh
Next 200 kWh @ 7.81¢/kWh
Over 300 kWh @ 4.95¢/kWh
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 5 :: Complete Tariff for Rate Code 5
Large Power Service
>1000kW Demand
Optional for >600 kW
Facility Charge: $100.00
Energy Charge:
All kWh"s @ 3.960¢/kWh
Demand Charge:
Non-coincident Demand $9.55/kW
Coincident Demand Monthly $6.59/kW
Seasonal Demand $9.57/kW
(Demand Charges adjusted for all Power Factors below 90%)
ECA: Rider 4
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 8 :: Complete Tariff for Rate Code 8
Heat Plus (8)
Energy Charge:
All kWh's @ 5.344 ¢/kWh
(Must be metered seperately)
Applies October thru May
ECA: Rider 5
Applicable Tax
Rate Code 11 or 12 :: Complete Tariff for Rate Code 11 or 12
Residential Time of Day (TOD) Service (11) or Residential All-Electric TOD Service (12)
Facility Charge: $19.00
Energy Charge:
On-Peak 4:01 pm to 9:00 pm All kWh's @ 25.57¢/kWh
Off-Peak 9:01 pm to 4:00 pm All kWh's @ 7.26¢/kWh
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 13 :: Complete Tariff for Rate Code 13
Commercial & Industrial & Three Phase Farm TOD
<75W Demand Jun, Jul, Aug, Dec, Jan, Feb
Facility Charge: $19.00 Single Phase/$40.00 Multi Phase
Energy Charge:
On-Peak 4:01 pm to 9:00 pm All kWh's @ 23.99¢/kWh
Off-Peak 9:01 pm to 4:00 pm All kWh's @ 6.57¢/kWh
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
Rate Code 14 :: Complete Tariff for Rate Code 14
Large Power TOD Service
>25W Demand
Facility Charge: $40.00
Energy Charge:
All kWh's @ 3.96¢/kWh
Demand Charge:
On-Peak 4:01 pm to 9:00 pm $16.93/kW of on-peak monthly billing demand
Off-Peak 9:01 pm to 4:00 pm $7.76/kW of off-peak monthly billing demand above on-peak demand
ECA: Rider 1
Applicable Tax
Additional minimum:
$0.75 per kVa>10 kVa
(Demand charges adjusted for all power factors below 90%)
Rate Code 16 :: Complete Tariff for Rate Code 16
Large General Service TOD Interruptible Service
>150 KW
Facility Charge: $100.00
|
Energy Charges: Demand Charges: |
Winter Winter |
Summer Summer |
|
|
||
Demand Charges adjusted for all Power Factors below 90%
ECA: Rider 6
Applicable Tax
Billing Demand shall be calculated as the larger of:
A. 75% of the billing demand in the previous June, July or August or
B. The sum of the contacted firm demand plus 50% of the maximum demand